Lamar Landing
Lamar Quick Trip
Commercial Infrastructure Development
Delivering Complex Utility Solutions With Precision
The Lamar Quick Trip project in Lamar, Colorado, showcased Unbridled Contractors’ expertise in managing high-risk utility and pipeline installations. Our team completed a 40-foot-deep manhole excavation and tied into the existing sanitary sewer system while navigating demanding site conditions and safety requirements.
The scope included installation of multiple utility systems—sanitary sewer, stormwater, and large-diameter pipelines—along with rock excavation, groundwater control, and the construction of stormwater vaults, forebays, and headwalls engineered for optimal flow management and water quality improvement.
HIGHLIGHTS
40-foot-deep sanitary manhole excavation and connection
Multi-system utility installation (sanitary, storm, and water)
Rock excavation and groundwater control operations
Construction of stormwater vaults, forebays, and headwalls
Three welded live taps on 24-inch steel main at 17 feet deep
Completed on time despite complex subsurface and coordination challenges
Delivering Complex Utility Solutions With Precision
The Lamar Quick Trip project in Lamar, Colorado, showcased Unbridled Contractors’ expertise in managing high-risk utility and pipeline installations. Our team completed a 40-foot-deep manhole excavation and tied into the existing sanitary sewer system while navigating demanding site conditions and safety requirements.
The scope included installation of multiple utility systems—sanitary sewer, stormwater, and large-diameter pipelines—along with rock excavation, groundwater control, and the construction of stormwater vaults, forebays, and headwalls engineered for optimal flow management and water quality improvement.
HIGHLIGHTS
40-foot-deep sanitary manhole excavation and connection
Multi-system utility installation (sanitary, storm, and water)
Rock excavation and groundwater control operations
Construction of stormwater vaults, forebays, and headwalls
Three welded live taps on 24-inch steel main at 17 feet deep
Completed on time despite complex subsurface and coordination challenges
UNBRIDLED SERVICES PROVIDED
- Heavy Civil & Utility Construction
- Site Development & Grading
- Water and Sewer Infrastructure
- Traffic Control & Safety Management
- Project Coordination & Quality Assurance
UNBRIDLED SERVICES PROVIDED
- Heavy Civil & Utility Construction
- Site Development & Grading
- Water and Sewer Infrastructure
- Traffic Control & Safety Management
- Project Coordination & Quality Assurance
Technical Execution and Coordination
The 40-foot manhole excavation required precision heavy-equipment operation, confined-space safety procedures, and the use of gas-protective lined manholes built for long-term durability. Additional deep sanitary installations reaching 30 feet and a complex bore under 6th Avenue off Highway 470 demanded constant coordination with CDOT, city officials, testing agencies, and the general contractor.
Technical Execution and Coordination
The 40-foot manhole excavation required precision heavy-equipment operation, confined-space safety procedures, and the use of gas-protective lined manholes built for long-term durability. Additional deep sanitary installations reaching 30 feet and a complex bore under 6th Avenue off Highway 470 demanded constant coordination with CDOT, city officials, testing agencies, and the general contractor.
Overcoming Site Challenges
Unique grading conditions and variable-depth concrete and asphalt preparation required continuous field adjustments and collaboration. The water-system installation was particularly demanding, featuring a complex testing sequence and three welded live taps on a 24-inch steel main set 17 feet deep—executed safely around active fiber, communications, and electrical utilities.
Right-of-way work added further complexity, involving exploratory excavation to locate unmapped utilities, many of which were discovered dangerously shallow. Despite these conditions, our team successfully delivered all infrastructure components on schedule.
Overcoming Site Challenges
Unique grading conditions and variable-depth concrete and asphalt preparation required continuous field adjustments and collaboration. The water-system installation was particularly demanding, featuring a complex testing sequence and three welded live taps on a 24-inch steel main set 17 feet deep—executed safely around active fiber, communications, and electrical utilities.
Right-of-way work added further complexity, involving exploratory excavation to locate unmapped utilities, many of which were discovered dangerously shallow. Despite these conditions, our team successfully delivered all infrastructure components on schedule.
Delivering Results That Last
The Lamar Quick Trip project reflects Unbridled Contractors’ commitment to precision, safety, and collaboration. By navigating complex subsurface conditions, coordinating with multiple stakeholders, and delivering critical infrastructure on schedule, we proved our ability to manage challenging utility and site-development projects from start to finish.
Delivering Results That Last
The Lamar Quick Trip project reflects Unbridled Contractors’ commitment to precision, safety, and collaboration. By navigating complex subsurface conditions, coordinating with multiple stakeholders, and delivering critical infrastructure on schedule, we proved our ability to manage challenging utility and site-development projects from start to finish.
Start Your Next Project With Confidence
Contact Us to discuss your infrastructure or site-development needs.
Start Your Next Project With Confidence
Contact Us to discuss your infrastructure or site-development needs.







